We received our first update from our PM today:
The footers and walls are in, the undergrounds for the plumbing are in and inspected by the county today, and the conduit for the electric is being installed today. The slab should be able to be poured on Tuesday and start framing on Wednesday. I attached a picture of what it looks as of this afternoon.
Short, sweet, and to the point! I plan on driving by in a few days to see for myself.
No comments:
Post a Comment